Bangkok and vicinity/Central | Bangkok, Pathum Thani, Nonthaburi, Nakon Pathom, Nakorn Nayok, Saraburi, Kanchanaburi, Ratchaburi, Ayutthaya, Lop Buri, Ang Thong, Sing Buri, Chai Nat, Uthai Thani, Samut Prakan, Samut Sakhon, Samuts Songkram, Supanburi, Petchaburi |
Eastern | Chon Buri, Rayong, Chachoengsao, Prachin Buri, Chanthaburi, Sra Kaeo |
Northern | Chiang Mai, Chiang Rai, Phitsanulok, Nakhon Sawan, Phichit, Uttaradit, Kamphaeng Phet, Sukhothai, Lamphun, Lampang, Phayao, (Petchaboon, Tak, Phrae and Nan will be considered by case) |
Northeastern | Nakhon Ratchasima, Khon Kaen, Buri Ram, Surin, Udon Thani, Ubon Ratchathani, Chaiyaphum, Sakon Nakorn, Roi Et, Nakorn Phanom, Mookdahan, Maha sarakham, Kalasin, Si Sa Ket, Amnat Chareon, Yasothon (Nong Khai, Bung kan, Nong Bua Lumpo, Loe will be considered by case) |
Southern | Prachuap Khiri Khan, Chumphon, Nakhon Si Thammarat, Surat Thani, Songkhla(Hat Yai), Phuket, Phatthalung, Krabi, Phangnga, Ranong (Trang, Satul will be considered by case) |
Service Conditions
1.The land must be easily accessed by large vehicles in the transporting of construction materials. This excludes any road tolls.
2. The main water pipe and main electricity cable must be available on your land in order to facilitate the construction of the home.
3. In case the public drainage system is not yet available on the land, the septic tank will be connected to the house drainage pipe.
4. The customer must be the land owner otherwise a letter of consent from the owner must be submitted.
The company provides these services to our customers.
No. | Description | Operation cost (baht) | Fee(baht) |
---|---|---|---|
1. | Apply for a construction permit (Company bears the expense) | - | - |
2. | Apply for construction permit (Company bear the expense) | - | - |
3. | Apply for a temporary water meter (Metropolitan) | 5,350 |
|
| Apply for a temporary water meter (Provincial) | 3,600 | 5,350 |
| (Company bears the expense excluding the service area extension fee) |
|
|
4. | Apply for a temporary electricity meter (Metropolitan) | 400 | 10,000 |
| Apply for a temporary electricity meter (Provincial) |
| 10,000 |
| (Company bears the expense service area extension fee) |
|
|
5. | Apply for a permanent water meter 1/2” (Metropolitan) | 107 | - |
| Apply for permanent water meter 1/2” (Provincial) | 535 |
|
| Customer bears the service area extension fee (if any) |
|
|
| Fees and deposit are covered by the company for the Exclusive II and Luxury II Series construction material (Service area extension fee excluded) |
|
|
6. | Apply for a permanent electricity meter (Metropolitan) |
|
|
| 15 Amps 1 Phase (Smart II Series) | 700 | - |
15 Amps 3 Phase (Exclusive II Series) | 700 | - | |
| 30 Amps 3 Phase (Luxury II Series) | 1,500 |
|
| Customer bears the service area extension fee (if any) |
|
|
| Fees and deposit are covered by company for the Exclusive II and Luxury II Series construction material (Service area extension fee excluded) |
|
|
7. | Apply for permanent electricity meter (Provincial) |
|
|
| 15 Amps 1 Phase (Smart II Series) | 700 | - |
| 15 Amps 3 Phase (Exclusive II Series) | 700 | - |
| 30 Amps 3 Phase (Luxury II Series) | 1,500 |
|
| Customers bears the service area extension fee (if any) |
|
|
| Fee and deposit are covered by company for the Exclusive II and Luxury II Series construction material (Service area extension fee excluded) |
|
|
The company will apply for the above services with the government authorities on your behalf until completed. In case the customers would like to change the size of the electricity meter specified by the company, please inform us on the day the contract is signed or prior to the beginning of the construction because the main cable must be prepared (additional cost).
In case you are interested to apply for housing loan service, we are pleased to facilitate the Bank on your behalf. The major banks that provide special conditions for our customers are
The basic conditions for housing loan are:
1. | The land must be free from any mortgage. In case there are co-owners, the co-owners must sign the letter of consent. |
2. | Land and building must be mortgaged to the bank. The owner must buy fire insurance policy with the insurer recommended by the bank. |
3. | Your monthly income (include your spouse) should be 2 times of the amount to be paid to the bank. For example, if the amount to be paid monthly is 10,000 baht, your monthly income should be 20,000 baht (approximately). |
PD House offers a variety of house designs for your selection or inspiration. Our professional sales consultant and architects are ready to provide expert advice, with the following details:
1. | We offer over 200 house designs to cater to all tastes and preferences, ensuring they meet the needs and status of everyone. You can make your decision, reserve, and proceed with construction with us immediately. |
2. | If our house designs do not fully meet your specific needs, we are happy to provide advice and make adjustments according to your preferences (any changes, whether additions or reductions, will be priced fairly based on actual construction costs). |
3. | If you wish to have a custom house design tailored specifically for you, we are pleased to offer specialized design services by expert architects, with consultation (the service fee is based on the standard rates of the Association of Siamese Architects). |
4. | When you decide to entrust PD House with the construction, the deposit will be considered part of the payment towards the house construction. |
1. | 20 years warranty for the structure of the house. Exclude the road and floor casted on ground. |
2. | 2 years warranty for general work for Exclusive II and Luxury II Series standard construction material 1 year warranty for general work for Smart II Series standard construction material. Exclude natural depreciation of materials due to long used and misused. |
3. | 5 years warranty for roof tiles (by the manufacturer and installer) |
4. | 10 years warranty for rustproof roof structure (by the manufacturer and installer) |
5. | 10 years warranty for laminated floor (by the manufacturer and installer) |
If you decide to have the company build your house, the Application form for house building service should be filled and submitted. Detail as follow:
No | House Price | Advance payment (Baht) |
1. | House price does not exceed 2 million baht | 30,000 |
2. | House price more than 2 million baht but not exceed 5 million baht | 50,000 |
3. | House price more than 5 million baht | 100,000 |
4. | Customers’ own house design | 3% |
Documents
1. 4 copies of Title Deed with verified signature (the same size of original copy)
2. 4 copies of ID card and house registration with verified signature
3. A copy of tax payment receipt with verified signature
Our survey officer will survey the land and the access road to the land to mark the lay out. If the construction site cannot be accessed due to too narrow road, the advanced payment will be refunded
When the land survey result, the list of standard materials and the house plan are agreed, the contract must be signed so the company can proceed for the construction permit.
The advance payment will be refunded on the day the contract is signed.
If there is any additional construction made after the contract is signed, the company will propose the quotation, and the payment must be made before the additional construction starts. The duration of construction dated from the day the contract is signed and the payment for the signing contract installment is fully paid. (The piles driving work will start after the contract signing 45-60 days approximately.)
Duration of construction for Pre-fabrication & Multi-Joint Lock System
(Since contract signing date)
No | House Price | Duration of construction |
1. | House price does not exceed 2 million baht | 8 - 9 Months |
2. | House price from 2 million baht but not exceed 4 million baht | 10 - 12 Months |
3. | House price from 4 million baht but not exceed 6 million baht | 13 - 14 Months |
4. | House price from 6 million baht but not exceed 10 million baht | 15 - 18 Months |
5. | House price from 10 million baht but not exceed 20 million baht | 19 - 21 Months |
6. | House price from 20 million baht but not exceed 30 million baht | 22 - 27 Months |
7. | House price from 30 million baht but not exceed 40 million baht | 28 - 35 Months |
8. | House price from 40 million baht but not exceed 50 million baht | 36 Months |
Duration of construction for Cast-in-place structure (since contract signing date)
No | House Price | Duration of construction |
1. | House price does not exceed 2 million baht | 10 - 11 Months |
2. | House price from 2 million baht but not exceed 4 million baht | 12 - 13 Months |
3. | House price from 4 million baht but not exceed 6 million baht | 14 - 15 Months |
4. | House price from 6 million baht but not exceed 10 million baht | 16 - 18 Months |
5. | House price from 10 million baht but not exceed 20 million baht | 19 - 23 Months |
6. | House price from 20 million baht but not exceed 30 million baht | 24 - 29 Months |
7. | House price from 30 million baht but not exceed 40 million baht | 30 - 35 Months |
8. | House price from 40 million baht but not exceed 50 million baht | 36 Months |
Remark:
For your confidence and to confirm that the company will complete the construction within the duration stated in the contract, the company agrees to pay the fine 0.01% of the house price if the company cannot hand over the house to the customers on time.
Term of Payment
Table of payment for Prefabrication & Multi-Joint Lock System
One storey house, price does not exceed 5 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
One storey house, price 5-10 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
One storey house, price 10 million baht up with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Two storey house, price not exceed 6 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Two storey house, price 6 -12 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Two storey house, price 12 -20 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Two storey house, price 20 million baht up with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Three storey house, price not exceed 8 million bath with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Three storey house, price 8 -15 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Three storey houses, price more than 15 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Four storey house, price not exceed 20 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Four storey houses, price exceed 20 million baht with Prefabrication & Multi-joint Lock System
Installment | Payment | Description |
Term of Payment
Table of payment for Cast-in-place System
One storey house, price not exceed 5 million baht with Cast-in-place structure
Installment | Payment | Description |
| 10% | On the contract signing date |
1. | 20% | Completion of setting out, piling work, foundation work and ground beams. |
2. | 20% | Completion of reinforced concrete structure work - column, floor, roof beam, concrete roof slab (if any) and swimming pool concrete pouring (if any). |
3. | 20% | Completion of galvanized roof truss installation, eaves installation (if any), roofing materials installation, brick laying, interior plumbing (with pressure tested), PVC conduit installation (for wiring) and 50% interior wall plastering. |
4. | 15% | Completion of wall plastering, interior wiring, bathroom floor and wall tiling, soffit-exterior ceiling, interior ceiling (except bathroom ceiling), skim coat plastering, skim coat plastering, primer painting and aluminum/vinyl doors and windows installation. |
5. | 10% | Completion of sanitary wares installation, treatment tank and drainage pipe installation, 1 final painting interior door panels installation and exterior wall decorative material installation (if any). |
6. | 5% | Completion of laminated floor installation, switches-outlets-lights installation, painting, interior air balancing system - PD Fresh Airflow installation and swimming pool system installation (if any) |
One storey house, price 5-10 million baht with Cast-in-place structure
Installment | Payment | Description |
| 10% | On the contract signing date |
1. | 15% | Completion of setting out, piling work, foundation work and ground beams |
2. | 15% | Completion of reinforced concrete structure work - columns, floors, roof beams, roof slab (if any), roof truss installation (if any), parking floor (if any) and concrete pouring for swimming pool (if any) |
3. | 15% | Completion of eaves installation (if any), roofing materials installation, 80% brick laying, internal plumbing (with pressure tested), |
4. | 15% | Completion of 100% brick laying, PVC conduit installation (for wiring) and 80% interior wall plastering (except bathroom wall). |
5. | 10% | Completion of 100% interior wall plastering, 80% exterior wall plastering, interior wiring, interior ceiling installation (except bathroom ceiling) |
6. | 10% | Completion of vinyl doors and windows installation, 100% exterior wall plastering, exterior ceiling installation, bathroom wall tiling and primer painting. |
7. | 5% | Completion of interior door panels installation, bathroom floor tiling, sanitary wares installation, treatment tank and drainage pipe installation, 1 final painting, and exterior wall decorative materials installation (if any). |
8. | 5% | Completion of flooring materials installation, switches-outlets installation, final painting, swimming pool system installation and completion of construction |
One storey house, price exceed 10 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out, piling work, and foundation work. | 10% |
2. | Completion of reinforced concrete structure work - columns, beams, floors, and concrete pouring for swimming pool (if any) | 10% |
3. | Completion of reinforced concrete structure work - roof beams, roof slab (if any), roof truss installation (if any), and 50% brick laying. | 10% |
4. | Completion of eaves installation (if any), roofing materials installation, 100% brick laying, and PVC conduit installation (for wiring). | 10% |
5. | Completion of internal plumbing (with pressure tested), 80% wall plastering and parking floor (if any). | 10% |
6. | Completion of 100% interior wall plastering, 50% exterior wall plastering, interior wiring, interior ceiling installation (except bathroom ceiling) | 10% |
7. | Completion of 100% exterior wall plastering and exterior ceiling installation. | 10% |
8. | Completion of vinyl doors and windows installation, and bathroom wall tiling and primer painting. | 10% |
9. | Completion of interior door panels installation, bathroom floor tiling, sanitary wares installation, treatment tank and drainage pipe installation, 1 final painting, and exterior wall decorative materials installation (if any). | 5% |
10. | Completion of flooring materials installation, switches-outlets installation, final painting, swimming pool system installation and completion of construction | 5% |
Two storey houses, price not exceed 3 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out, piling work, foundation work and ground beam. | 10% |
2. | Completion of reinforced concrete structure work – 1st floor columns, floor and 2nd floor beams. | 15% |
3. | Completion of reinforced concrete structure work – 2nd floor columns, floor and roof beams. | 15% |
4. | Completion of roof truss installation (except lower roof), fascia (if any), roofing materials installation (except lower roof-later) and 50% brick laying. | 15% |
5. | Completion of 100% brick laying, internal plumbing (pressure tested), PVC conduit installation (for wiring), and 50% interior wall plastering. | 10% |
6. | Completion of 100% wall plastering, exterior ceiling installation, bathroom wall tiling, vinyl doors and windows installing, interior ceiling installation, interior wiring, lower roof truss and roofing material installation (if any) and primer paint. | 10% |
7. | Completion of bathroom floor tiling, stairs installation, sanitary wares installation, treatment tank and drainage pipe installation, internal door panels installation and 1 final painting. | 10% |
8. | Completion of flooring materials, switches-outlets installing, final painting and completion of construction. | 5% |
Two storey house, price 3 -10 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out, piling work and foundation work | 10% |
2. | Completion of reinforced concrete structure work – 1st floor beams, columns, and floor. | 10% |
3. | Completion of reinforced concrete structure work – 2nd floor beams, columns, and floor. | 10% |
4. | Completion of reinforced concrete structure work - roof beam, roof truss installation (except lower roof) and 50% brick laying, | 10% |
5. | Completion of fascia (if any), roofing materials installation (except lower roof-later) and 100% brick laying, internal plumbing (pressure tested), PVC conduit (for wiring) installation and parking floor (if any) | 10% |
6. | Completion of 80% interior wall plastering, 50% exterior wall plastering and internal wiring. | 10% |
7. | Completion of 100% wall plastering, exterior ceiling and interior ceiling installation (except bathroom ceiling) | 10% |
8. | Completion of vinyl doors and windows installation, bathroom floor and wall tiling and primer painting. | 10% |
9. | Completion of internal door panels installation, stairs installation, sanitary wares installation, treatment tank and drainage pipe installation, 1 final painting. | 10% |
10. | Completion of flooring materials, switches-outlets installing, final painting and completion of construction. | 5% |
Two storey house, price 10-20 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out and piling work | 10% |
2. | Completion of reinforced concrete structure work – foundation, 1st floor beams and columns | 10% |
3. | Completion of reinforced concrete structure work – 1st floor concrete floor, and 2nd floor beam. | 10% |
4. | Completion of reinforced concrete structure work – 2nd floor columns and floor | 10% |
5. | Completion of reinforced concrete structure work - roof beam, 50% brick laying, roof truss installation (except lower roof) | 10% |
6. | Completion of roofing materials and fascia (if any) installation (except lower roof), 100% brick laying, PVC conduit installation (for wiring) and 50% interior wall plastering. | 10% |
7. | Completion of 100% interior wall plastering, internal wiring, internal plumbing (pressure tested) and 50% exterior wall plastering. | 5% |
8. | Completion of 80% exterior wall plastering, exterior and interior ceiling installation (except bathroom ceiling) | 5% |
9. | Completion of 100% exterior wall plastering, vinyl door and window installation, internal door installation, bathroom wall tiling and lower roof truss and roofing material installation (if any) | 5% |
10. | Completion of bathroom floor tiling, primer painting and1 final painting. | 5% |
11. | Completion of stairs installation, sanitary wares installation, treatment tank and drainage pipe installation | 5% |
12. | Completion of flooring materials, switches-outlets installation, final painting, and completion of construction. | 5% |
Two storey houses, price exceed 20 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out and piling work | 10% |
2. | Completion of reinforced concrete structure work – foundation, 1st floor beams and columns. | 10% |
3. | Completion of reinforced concrete structure work – 1st floor concrete floor, and 2nd floor beam. | 10% |
4. | Completion of reinforced concrete structure work – 2nd floor columns and floor | 10% |
5. | Completion of reinforced concrete structure work - roof beam and roof truss installation (except lower roof) | 5% |
6. | Completion of roofing materials and fascia (if any) installation (except lower roof-later) and 50% brick laying. | 5% |
7. | Completion of 100% brick laying and PVC conduit installation (for wiring) | 5% |
8. | Completion of 50% interior wall plastering, internal plumbing (with pressure tested) | 5% |
9. | Completion of 100% interior wall plastering, internal wiring, and interior ceiling installation (except bathroom ceiling). | 5% |
10. | Completion of 80% exterior wall plastering, lower roof truss and roofing material (if any) installation | 5% |
11. | Completion of 100% exterior wall plastering, exterior ceiling and 50% bathroom wall tiling. | 5% |
12. | Completion of vinyl doors and windows installing, bathroom wall tiling and primer painting. | 5% |
13. | Completion of interior doors installation, bathroom floor tiling, 1 final painting. | 5% |
14. | Completion of stairs and flooring materials installation, sanitary wares installation, treatment tank and drainage pipe installation. | 3% |
15. | Completion of switches-outlets installing, final painting and completion of construction. | 2% |
Three storey house, price not exceed 7 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out, piling work, reinforced concrete structure work - foundation and ground beam. | 10% |
2. | Completion of reinforced concrete structure work – 1st floor columns, floor and 2nd floor beam | 10% |
3. | Completion of reinforced concrete structure work – 2nd floor columns, floor and 3rd floor beam | 10% |
4. | Completion of reinforced concrete structure work – 3rd floor columns, floor and roof beam | 10% |
5. | Completion of roof truss and eaves (if any) installation (except lower roof), roofing materials installation (except lower roof) and 50% brick laying | 10% |
6. | Completion of 100% brick laying, PVC conduit installation (for wiring), 80% interior wall plastering, internal plumbing (with pressure tested), and 50% exterior wall plastering | 10% |
7. | Completion of 100% interior-exterior wall plastering, exterior and interior ceiling installation (except bathroom ceiling), bathroom wall tiling, internal wiring and lower roof truss and roofing material (if any) installation | 10% |
8. | Completion of bathroom floor tiling, vinyl doors and windows installation and primer painting | 10% |
9. | Completion of stairs installation, sanitary wares installation, treatment tank and drainage pipe installation, interior doors installation, 1 final painting and exterior wall decoration material installation (if any) | 5% |
10. | Completion of flooring materials, switches-outlets installation, final painting and completion of construction. | 5% |
Three storey house, price 7-15 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out, piling work, reinforced concrete structure work - foundation and ground beam. | 9% |
2. | Completion of reinforced concrete structure work – 1st floor columns, floor and 2nd floor beam and concrete pouring for swimming pool (if any) | 8% |
3. | Completion of reinforced concrete structure work – 2nd floor columns, floor and 3rd floor beam | 8% |
4. | Completion of reinforced concrete structure work – 3rd floor columns, floor and roof beam | 8% |
5. | Completion of roof truss and eaves (if any) installation (except lower roof), roofing materials installation (except lower roof) and 50% brick laying | 8% |
6. | Completion of 100% brick laying and internal plumbing (with pressure tested), | 8% |
7. | Completion of 80% interior wall plastering (except bathroom wall), PVC conduit installation (for wiring) and parking floor (if any) | 8% |
8. | Completion of 100% interior wall plastering, 50% exterior wall plastering, internal wiring and interior ceiling installation (except bathroom ceiling) | 8% |
9. | Completion of 100% exterior wall plastering, exterior ceiling installation, 50% bathroom wall tiling and lower roof truss and roofing material (if any) installation | 5% |
10. | Completion of 100% bathroom wall tiling, vinyl doors and windows installation and primer painting | 5% |
11. | Completion of interior doors installation, bathroom floor tiling and 1 final painting | 5% |
12. | Completion of stairs and flooring materials installation, sanitary wares installation, treatment tank and drainage pipe installation. | 5% |
13. | Completion of switches-outlets installation, final painting, swimming pool system installation (if any) and completion of construction. | 5% |
Three storey house, price exceed 15 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out and piling work | 8% |
2. | Completion of reinforced concrete structure work – foundation, and 1st floor beams. | 7% |
3. | Completion of reinforced concrete structure work – 1st floor columns, floor and 2nd floor beams and concrete pouring for swimming pool. | 7% |
4. | Completion of reinforced concrete structure work – 2nd floor columns, floor and 3rd floor beams | 7% |
5. | Completion of reinforced concrete structure work – 3rd floor columns, floor and roof beams | 7% |
6. | Completion of roof truss and eaves (if any) installation (except lower roof), roofing materials installation (except lower roof) and 50% brick laying | 7% |
7. | Completion of 100% brick laying and internal plumbing (with pressure tested) | 7% |
8. | Completion of 80% interior wall plastering (except bathroom wall), PVC conduit installation (for wiring) and parking floor (if any) | 7% |
9. | Completion of 100% interior wall plastering, 50% exterior wall plastering, internal wiring and interior ceiling installation (except bathroom ceiling), | 6% |
10. | Completion of 100% exterior wall plastering, 50% bathroom wall tiling and lower roof truss and roofing material (if any) installation | 6% |
11. | Completion of vinyl doors and windows installation, bathroom wall tiling, and primer painting | 6% |
12. | Completion of interior doors installation, bathroom floor tiling and1 final painting. | 5% |
13. | Completion of stairs and flooring material installation, sanitary wares installation, treatment tank and drainage pipe installation. | 5% |
14. | Completion of switches-outlets installing, final painting, swimming pool system installation (if any) and completion of construction. | 5% |
Four storey house, price not exceed 20 million baht with Cast-in-place structure
Installment | Description | Payment |
| On contract signing date | 10% |
1. | Completion of setting out, piling work and reinforced concrete foundation work. | 7% |
2. | Completion of ground beams | 7% |
3. | Completion of reinforced concrete structure work – 1st floor columns, floor and 2nd floor beam and floor. | 7% |
4. | Completion of reinforced concrete structure work – 2nd floor columns, and 3rd floor beams, floor and columns. | 7% |
5. | Completion of reinforced concrete structure work – 4th floor beams, floor, columns and roof beams. | 7% |
6. | Completion of roof truss and eaves (if any) installation (except lower roof), roofing materials installation (except lower roof) and 50% brick laying | 7% |
7. | Completion of 100% brick laying and internal plumbing (with pressure tested) | 5% |
8. | Completion of 80% interior wall plastering (except bathroom wall), PVC conduit installation (for wiring) and parking floor (if any) | 7% |
9. | Completion of 100% interior wall plastering, 50% exterior wall plastering, internal wiring and interior ceiling installation (except bathroom ceiling) | 8% |
10. | Completion of 100% exterior wall plastering, exterior ceiling installation, 50% bathroom wall tiling and lower roof truss and roofing material (if any) installation | 8% |
11. | Completion of vinyl doors and windows installation, bathroom wall tiling, and primer painting | 8% |
12. | Completion of interior doors installation, bathroom floor tiling and1 final painting. | 7% |
13. | Completion of stairs and flooring material installation, sanitary wares installation, treatment tank and drainage pipe installation. | 3% |
14. | Completion of switches-outlets installing, final painting and completion of construction. | 2% |
Four storey house, price exceed 20 million baht with Cast-in-place structure
Installment | Description | Payment |
| On the contract signing date | 10% |
1. | Completion of setting out, piling work and reinforced concrete foundation work. | 7% |
2. | Completion of ground beams | 7% |
3. | Completion of reinforced concrete structure work – 1st floor columns, floor and 2nd floor beam and floor. | 7% |
4. | Completion of reinforced concrete structure work – 2nd floor columns, and 3rd floor beams, floor and columns. | 7% |
5. | Completion of reinforced concrete structure work – 4th floor beams, floor, columns and roof beams. | 7% |
6. | Completion of roof truss and eaves (if any) installation (except lower roof), roofing materials installation (except lower roof) | 7% |
7. | Completion of 80% brick laying and internal plumbing (with pressure tested) | 5% |
8. | Completion of 100% brick laying and PVC conduit installation (for wiring) | 5% |
9. | Completion of 80% interior wall plastering (except bathroom wall) and parking floor (if any) | 7% |
10. | Completion of 100% interior wall plastering, 50% exterior wall plastering, internal wiring and interior ceiling installation (except bathroom ceiling), | 5% |
11. | Completion of 100% exterior wall plastering, exterior ceiling installation, 50% bathroom wall tiling and lower roof truss and roofing material (if any) installation | 7% |
12. | Completion of vinyl doors and windows installation, 100% bathroom wall tiling, and primer painting. | 7% |
13. | Completion of interior doors installation, bathroom floor tiling and1 final painting. | 7% |
14. | Completion of stairs and flooring material installation, sanitary wares installation, treatment tank and drainage pipe installation. | 3% |
15. | Completion of switches-outlets installing, final painting and completion of construction. | 2% |