The heart of our business id appreciate to provide you with our dedecated service.
"PD HOUSE" is devote to serve you every procedures in biulding your dream house on your hand.Our wide selections of house designed are ready to be the house of your choice.We have many solid teams of staff with more than 14 years experience to build the same quality house to your satisfactions.
For The home construction has many procedures and relate to many government office involve to the work such as registration for construction permit, Application for electrical and water supply , registration for home address , application for telecommunication , running process for home morgate from finance Institute and also warrantee , consultancy etc.
We are fully understood this complicated procedures. We appreciate to serve those processes for you to minimize your expenses as followings.
Location of service areas
The area in Thailand are available to sevices as following
The land for construction site shall available transportation for delivery construction materials to site.In case of there are other expenses such as tollway, preparing of access road etc.These expenses shall extra of construction budget.
The land shall on area of government facilities service areas both main electrical and main water supply.For the land with out public drainage system, we will provide a seep tank for drainage system.
The land must fully authorize belong to the house owner,If not,shall legality allowable from the land owners.
Model
1
We have more than 200 house designs for your choice. They will suit for any kinds of taste and up to your financial status.Y ou can select your favorite design, make a reservation and have us build your house at once.
2
If our designs don't exactly meet your need,we are happy to modify the design as you like.(The changes of the design may cost less or more)
3
If you want us to make a new design,our experienced architect will be happy to do that for you and give you advice.(The fee for the design is on the standard defined by the Siam Architecture Association.)
4
If you agree to have us build you house,the reservation deposit is included in the price of the house. If you want someone else to build your house,the reservation deposit will be refunded.
General services
The company provides these services to our customers
Item
Services
Services Charge
Free
1
Ask for building permission
-
-
2
Ask for house number
-
-
3
Ask for temporary water meter
-
-
4
Ask for temporary electricity meter
-
-
5
Ask for permanent water meter dia .3/4”
-
-
6
Ask for permanent electricity meter
- 15 Amps. For smart Series
- 30 Amps. For Platinum Series
-
-
-
-
7
Ask for telephone installment
-
As billed
Housing Loan Service
The company will provide the service of the 7 items above with no charge. If the customer needs the electricity meter larger than the one that the company specified , please inform us when the contracted is signed or prior to the construction begin.
If the customer wants to get the housing loan from bank , we will be a co-ordinator between the customer and the banks. The banks we have connection now are Siam Commercial Bank (www.scb.co.th) and Government Housing Bank (www.ghb.co.th). To apply for the loan , the following items are considered :-
1. The land is free from any mort gage bond and if there is a co-right holder , he or she must comply to be a co-mortgagor.
2. The land and the building must be mortgaged with the bank and insured against fire with the insurance company the band defined.
3. You monthly income (together with your spouse) triple the monthly payment.( e.q. your payment is 10,000your income should 30,000 Bath
Construction Procedures
Home morgate services
We are appreciate to service you for home mortgage procedure finance institute for your available of construction payment as the following principles
1
The land shall free of any deposit.
2
Land and home had to deposit to finance institute and also issuing assurance premium
3
Your incomes three times of monthly refund.
Guarantee
1
Guarantee period for ain structural of house 15 years except entrance pavement and floor on ground which may regular naturally settlementation.
2
General guarantee 3 years except the depreciation due to long live material or incorrect usage.
3
Guarantee for termites prevent system 3 years by our representative termite business companies.
4
5 years guarantee for roof liles installations.
Reservation
For your agree to build you house, the reservation shall be born, The process as following.
ITEM
DESCRIPTION
RESERVATION INSTALLMENT (BAHT)
1
Cost of house less than 3 million
50,000
2
Cost of house more than 3 million
100,000
3
The houses which is your completed drawing (Drawing of customer)
3% (not exceed) 100,000
Documentation
1.
4 copies of the title deed to a piece of land.
2.
4 copies of I.D. card and Home registered.
3.
1 copy of Land Tax reciept.
We will invitigate your land according to access road, house location, and facilities for construction.If not aviliable access road,we agreed to reimburse the reservation.
Agreement
After land investing , design , and all materials are all suitably and satisfaction. Building contact agreement shall on process for the procedure to start construction later. We will refund the deposited money on the construction contract sinning dated. In case , there are some alternative after those day respectively. The negotiation to conclude every alternate and the cost due to change order shall paid in advance for construction
Construction Period
The construction period begin on the signing contract dated until the completed construction works construction periods as followings.
ITEM
CONSTRUCTION COST
CONSTRUCTION PERIOD
1
Cost less than 2 million baht
9 - 10 months
2
Cost 2 Million baht and not more than 4 Million baht
11 - 13 months
3
Cost 4 Million baht not more than 6 Million baht
14 - 15 months
4
Cost 6 Million baht not more than 10 Million baht
16 - 19 months
5
Cost More than 10 Million baht
19 months or more
Remark
1.The specified construction period shall extend 30 days for construction the other designed home or out of Patum Design develop co.,ltd. standard plan.
2. Panualty shall be born 300 baht per day for the construction cost not 4 million and 500 baht per day for construction case more than 4 million baht from the end of Contract period date.
Term of payment for cast in place structure
One storey house
INSTALLMENT
PAYMENT(%)
DESCRIPTION
10
On the contract signing date.
1
20
Completed of Locate lay out, Piling work,Foundations and Groud beams
2
20
Compelted of Column, First floor conerete casting, Roof beams.
3
20
Completed of Roof truss, roof tiles, Mason and Erection frames of door and window 80 % (Except UPVC doors and windows)
4
15
Completed of Plastering , Ceiling (except ceiling of toilets) , Interior plumbing, Interior wiring.
5
10
Completed of Toilets Tiles , Doors and Windows panel installation , Primer painting.
6
5
Completed of Remaining works and Handover.
Two storey house which construction cost less than 3 million baht.
INSTALLMENT
PAYMENT(%)
DESCRIPTION
10
On the contract signing date.
1
10
Completed of Locate lay-out , Piling works , Foundations , Ground beams.
2
15
Completed of Columns for second floor, First floor concrete casting,Beam for second Floor.
3
15
Completed of Columns for roof beams. Second floor concrete casting, Roof beams.
4
15
Completed of Roof trusses Roof tiles (Top level only), Mason and Erection frames of door and window 50 % (Except UPVC door and windows)
5
10
Completed of Interior plastering. Interior plumbing , Interior wiring.
6
10
Completed of Exterior plastering, Doors and Windows panel installation , Ceiling ( Except Ceiling of toilets )
7
10
Completed of All floor surface materials , Stairs , Toilet tiles ,Primer painting.
8
5
Completed of Remaining works and Handover.
Two storey house which construction cost more than 3 Million Baht But not more than 10 million baht.
INSTALLMENT
PAYMENT(%)
DESCRIPTION
10
On the contract signing date.
1
10
Completed of Locate lay - out , Pilling wors, Foundations.
2
10
Completed of Ground beams , First floor concrete casting ,Columns for second floor.
3
10
Completed of Beams for second floor , Columns for roof bean , Second floor concrete casting.
4
10
Completed of Roof beams , Roof trusses , Mason and Erection frames of door and window 50% (Except UPVC doors and windows )
5
10
Completed of Roof tiles, (top level only ) , Interir plumbing , Mason and Erection frames of door and window 50 % , (Except UPVC doors and windows ) , Interior conduit forwiring.